2024 Mill and Overlay Project
Cherry Hills Village Public Works will be performing Mill and Overlay Asphalt Operations to the streets in this area. During the process, the streets may be temporarily closed. Please follow all construction signage and flagger directions. This project is scheduled to start July 22nd, 2024 (weather pending). For more information call 303-783-2741 or 303-783-2744. Thank you for your patience. This schedule is weather permitting.
- Locations:
- Site #1: Hudson Pkwy and Quincy Avenue
- Site #2: Cherryridge Road and University Blvd
- Site #3: Frankin Street and Quincy Avenue
- Site #4: Oxford and Humbolt Street
- Project Progression (All Weather & Equipment dependent)
- Will work: East to West
- Will Start on 7/22 and complete by weeks end 8/2/24)
- Day #1: Mill Site #1 and Site #2
- Day #2: Overlay Site #1 and Site #2
- Day #3: Mill and overlay Site #3
- Day #4: Mill Site #4 (Will most likely be done on 7/29/24) – Cannot leave a road milled over the weekend which is the reason we will move this work to the following Monday.
- Day #5: Overlay Site #4 (Will be done on 7/30/24)
For more information on Mill and Overlay